What's New
About Us

India's Investment Climate

Highlights of Union Budget 1997-98

Highlights of Union Budget

Frequently Asked Questions by NRIs

Some Useful Contact Addresses



POLICY ON HYDRO POWER DEVELOPMENT

 


                          

          1.   NEED FOR A HYDEL POLICY

               Hydro power  is  a  renewable  economic  non  polluting  and
          environmentally  benign  source of energy.   Hydro Power stations
          have inherent ability for instantaneous starting, stopping,  load
          variations  etc.  and  help  in  improving  reliability  of power
          system.   Hydro stations are the best choice for meeting the peak
          demand.    The  generation  cost  is  not only inflation free but
          reduces with time Hydroelectric projects have  long  useful  life
          extending  over  50  years  and  help in conserving scarce fossil
          fuels.   They also help in opening of avenues for development  of
          remote and backward areas.

               Our   country   is   endowed   with   enormous  economically
          exploitable and viable  hydro  potential  assessed  to  be  about
          84,000  MW  at  60% load factor (1,48,700 MW installed capacity).
          In addition,  6781.81 MW in  terms  of  installed  capacity  from
          small,  mini  and micro hydel schemes have been assessed.   Also,
          56,  sites for pumped storage schemes with an aggregate installed
          capacity of 94,000 MW have been indentified.   However,  only 15%
          of the hydroelectric potential has been harnessed so far  and  7%
          is  under  various  stages  of  development.    Thus,  78% of the
          potential remains without any plan for exploitation.

               Despite hydroelectric projects being recognised as the  most
          economic  and  preferred  source  of electricity,  share of hydro
          power has been declining steadily scine 1963.  The share of hydro
          power has been  continuously  declining  during  the  last  three
          decades.    The hydro share has declined from 44 per cent in 1970
          to 25  per cent in 1998.   The ideal hydro thermal mix should  be
          in  the  ratio  of  40:60.   Because of an imbalance in the hydel
          thermal mix especially in the Eastern and Western  regions,  many
          thermal  power stations are required to back down during off peak
          hours.  The capacity  of  the  thermal  plants  cannot  be  fully
          utilised  resulting  in  a  loss  of about 4 to 5 per cent in the
          plant load factor.   Even if the share of hydro power  is  to  be
          maintained  at  the  existing level of 25 per cent,  the capacity
          addition during the 9th and 10th Plan would work  out  to  23,000
          MW.  If  the  share were to be enhanced to 30 per cent,  it would
          require a further addition of 10,000 MW of hydro capacity.

               The constraints which have affected  hydro  development  are
          technical  (difficult  investigation,  inadequacies in tunnelling
          methods),   financial  (deficiencies  in  providing   long   term
          financing), tariff related issues and managerial weaknesses (poor
          contract  management).    The hydro projects are also affected by
          geological surprises (especially in the  Himalayan  region  where
          underground tunnelling is required), inaccessibility of the area,
          problems  due  to delay in land acquisition,  and resettlement of
          project affected familities,  law and order problem  in  militant
          infested areas.

          2.   OBJECTIVES

               The programmed capacity addition from hydel projects during
          the 9th Plan is 9815 MW, of which Central Sector and State Sector
          will  contribute 3455 MW and 5810 MW respectively and the balance
          550 MW  will be contributed by the Private  Sector.    Sanctioned
          and  ongoing  schemes under implementation will enable a capacity
          addition of 6537 MW during the 10th Plan,  of which 990 MW,  4498
          MW  and  1050  MW will be the contribution of Central,  State and
          Private Sectors respectively.  In addition, 12 projects (5615 MW)
          have been identified for advance  action  in  the  9th  Plan  for
          benefits in the 10th Plan.

               The Government of India has set the following objectives for
          acelerating the pace of hydro power development:-

          (i)  Ensuring targeted capacity addition during 9th Plan

               The  9th  Plan programme envisages capacity addition of 9815
               MW from hydel projects in the  total  capacity  addition  of
               40245   MW.     The  Central  Sector  hydel  projects  would
               contribute 3455 MW,  State Sector  would  add  5810  MW  and
               Private Sector 550 MW.  Keeping in view that the achievement
               in 8th Plan had been dismal, the Government is determined to
               ensure that no slippage is allowed to occur and the targeted
               capacity addition in the 9th Plan is achieved in full.

          (ii) Expoloitation  of  vast  hydroelectric potential at a faster
               pace:

               The Government would initiate advance action for  taking  up
               new   hydro   projects   since  the  ongoing  projects  will
               contribute a very small percentage of the  desired  capacity
               addition envisioned for 10th plan and beyond.   Towards this
               end,  Government would take up for  execution  all  the  CEA
               cleared  projects,  and  take  steps  to  update  and obtain
               clearances  for  pending  DPRs.    Measures  for  vigorously
               starting survey and investigations for new green field sites
               would also be implemented shortly.   In addition, Government
               is keen to restart and activate the hydro projects which are
               either languishing  for  want  of  funds  or  are  remaining
               dormant due to unresolved inter-State issues.

          (iii)Promoting small and mini hydel projects

               Small  and  mini  hydel potential can provide a solution for
               the  energy  problems  in  remote  and  hilly  areas   where
               extension  of  grid system is comparatively uneconomical and
               also along the canal  systems  having  sufficient  drops.The
               small  hydro  potential  could  be developed economically by
               simple design of turbines,  generators and the civil  works.
               Small and mini hydel capacity aggregating to about 340 MW is
               in opeation,  and Government is determined to provide thrust
               for developing the  assessed  small  hydel  potential  at  a
               faster pace henceforth.

          (iv) Strengthening  the role of PSUs/SEBs for taking up new hydel
               projects:

               In view of the poor response  of the private sector  so  far
               in  hydro development which may persist for some more years,
               the involvement of public sector in hydel projects would not
               only have to continue but will also  have  to  be  enlarged.
               There   are   categories   of   projects   such   as  multi-
               purpose,projects involving inter-State issues,  projects for
               peaking   power   and  those  involving  rehabilitation  and
               resettlement which may be  taken  up  and  implemented  more
               easily in public sector.    Similiarly,  mega hydro projects
               in North and North Eastern region  would  also  have  to  be
               executed by CPSUs in case the State or the private sector is
               not in position to implement these projects.

          (v)  Increasing private investment

               Even  though  public  sector  orgations would play a greater
               role in the development of new schemes, this alone would not
               be adequate to develop the  vast  remaining  hydro  potental
               since  it  will require huge investments which are difficult
               to be supported from the  budget/plan assistance in view  of
               competing  demands  from  the  various  sectors.   A greater
               private investment through IPs and joint ventures  would  be
               encouraged  in  the  coming  years  and required atmosphere,
               incentives and reliefs would be provided  to  stimulate  and
               maintain a trend in this direction.

          3.   Policy Instruments

               To   achieve   the   above   stated  objectives  for  faster
          development of hydro potential,  the Government proposes to  take
          the following steps and measures:-

          3.1  Funding

               All the ongoing Central Sector hydroelectric projects namely
          Nathpa  Jhakri  (1500  MW),  Tehri  State 1 (1000 MW),  Ranganadi
          State  1  (405MW),  Dulhasti  (390  MW),  Dhauliganga  (280  MW),
          Doyang(75MW)  and  Rangit  (60  MW)  would  be provided with full
          budgetary support till completion.  Government of India will also
          provide budgetary support for the new projects to be taken up  by
          the  CPSUs  during  the 9th Plan.   The actual utilisation of the
          funds on the ongoing  Central  Sector  hydel  projects  has  been
          Rs.1616.87 crores in 1997-98 and the budget provision for 1998-99
          has been increased to Rs.2070 crores.   Therefore,  the remaining
          three years of the 9th plan would require about Rs.5896 crores on
          the ongoing Central Sector  projects  (excluding  NEC  Projects).
          Having  regard  to  the  large capacity addition envisaged in the
          State Sector (510MW) it is necessary to (a) provide  a  mechanism
          for  funding  hydro  projects  by  earmarking  funds  in the plan
          allocation of the State Governments by the  Planning  Commission;
          and  (b)  organisation  supplementary  funding  funding  of hydel
          projects where more than 50  per  cent  of  the  expenditure  has
          already been incurred.

               The   monitoring   of  all  the  ongoing  projects  will  be
          intensified and a  task  force  would  be  constituted  for  this
          purpose.    The  progress  of important projects in the State and
          Central   Sector   would   be   reviewed   at   the   level    of
          Minister/Secretary(Power)  and all measures will be taken so that
          there is no slippage  in  the  schedule  for  completion  of  the
          ongoing projects.

          3.2  Power Development Fund

               The  survey  and  investigation  of hydro projects have been
          discontinued since long in the State due to paucity of funds.  As
          a result,  there are not enough projects right now that could  be
          taken  up  in the next 2 to 3 years and get completed in the 10th
          Plan or early 11th Plan.  It is necessary to carry out survey and
          investigations continuously and prepare a shelf of  projects  for
          execution over a decade and more.

               In  case  fully  investigated projects with Detailed Project
          Reports are offered to proviate developers,  their response could
          be more favourable.   If pre-construction activities and enabling
          works could be completed and these  sites  eoffeed  to  IPPs  the
          chances  of  IPPs opting to invet in these projects would further
          improve.   Further this would reduce the gestation  period  which
          would make investment in hydro projects more attractive.

               The  above  approach  is  possible  and successful only if a
          dedicated fund is available for this purpose.

               It is proposed to levy a Power Development Cess at 10  paise
          per kwh of electricity consumed in the country.  The levy of cess
          was  recommended  by  the  Sub  Committee of the NDC Committee on
          Power which gave its report in January, 1994.   The cess would be
          levied    on   the   electricity   billed   by   SEBs/Electricity
          Departments/Bulk licensees/Distribution licensees.   The State/UT
          Governments  would be responsible for the collection of the cess.
          The amount would thereafter be  credited  to  a  "National  Power
          Development  Fund.   It is expected that about Rs.3000 crores per
          annum can be realised by levying a cess of 10 paise per kwh.

               It  would  be   necessary   to   establish   a   legal   and
          organisational frame work for levy of a cess.   Electricity being
          a Concurrent Subject,  the Central  Government  is  empowered  to
          legislate  on  all  aspects  of electricity including the levy of
          cess,  the  proceeds  of  which  is  to  be  utilised  for  power
          development.  In order to levy a Power Development Cess, it would
          be  necessary  for  Parliament  to  enact  a  legislation  on the
          subject.   The  cess  will  be  imposed  on  the  consumption  of
          electricity throughout the country.  The State Electricity Boards
          will be the responsible agencies for the collection of cess.  The
          proceeds of the cess will be shared with State/UT Governments and
          the  Central  Government.   Two-thirdsof the amount realised from
          the State/UT Government  will  be  allocated  to  the  respective
          government  to  be  utilised for power development.   This amount
          would be released from the National Power  Development  Fund  for
          financing  schemes/projects  recommends  by the State Government.
          The  remaining  one-third  will  be  utilised  by   the   Central
          Government for promoting hydel projects in the Central Sector and
          for investment in transmission lines for evacuation of power from
          mega hydel projects which will benefit more than one State.

          3.3  Basin-wise Development of Hydro Potential

               The   assessment   of  hydro  potential  in  845  identified
          conventional hydro projects and 56 pumped storage projects is  on
          the  basis  of  desk studies using toposheets and discharge data.
          Further,  detailed studies to  firm  up  the  parameters  of  the
          projects  as  identified by CEA would be taken up on the basis of
          development of  hydro  potential  in  a  basin  as  a  whole  for
          maximising  benefits  and  prioritising  execution  of  projects.
          These studies will be done in close co-ordination with CWC and in
          harmony with Planning Commission and development for  other  uses
          of  water  like irrigation,  drinking water etc.  While CEA would
          carry  out  these  studies,   DCPSUs/other   Central   Government
          Organisations  and  State authorities would do the investigations
          and  prepare  the  detailed  project  reports,   by  adopting  an
          integrated  approach  towards  planning  and  development  of the
          various projects, evacuation arrangement and environmental impact
          assessment.   This would enable an optimal  harnessing  of  hydro
          potential in each river basin.

          3.4  Advance Action for Capacity Addition in the 10th plan and
               beyond

               Government  will  take  immediate  steps  to tie up funding,
          execution agencies and convey  investment  decision  for  schemes
          already  accorded  techno  economic clearance of CEA.   As far as
          Central Sector is concerned,  NHPC would take up Chamera Stage II
          (300  MW),  Parbati Stage-II (800 MW),  HP and Kol Dam (800MW) in
          HP;  Teesta Stage V(510 MW) in Sikkim,  Loktak Downstream (90 MW)
          in  Manipur  and  NEEPCO will take up Tuivai (210 MW) in Mizoram,
          Lower Kopili (150MW) in Assam,  Kameng  (600  MW)  and  Ranganadi
          Stage  II (160 MW) in Arunachal Pradesh (after the consent of the
          State Govt.  has been obtained).   In addition  THDC  would  take
          action  to  start  activities  on  Tehri  Stage  II (1000 MW) and
          Koteshwar (400 MW) in UP.   Similarly NJPC  would  also  take  up
          Rampur  Project  (535  MW)  in HP.   These projects would require
          budgetary support of about Rs. 2000 crores in the 9th Plan.


               As a long term strategy efforts will be made to ensure  that
          DPRs  which  are under various stages of processing for accord of
          TEC by CEA are finalised and cleared so that  a  start  could  be
          made on these projects in the next one or two years.   Survey and
          investigation  of  the  potential  hydro  sites  on  an  advanced
          scientific  basis  would be essential requirement for the future.
          The progress on this  front  has  been  dismal  given  the  funds
          constraint  and  outdated technology.   The funding agencies like
          World Bank and ADB have shown their interest towards funding  the
          survey  and  investigation activities for hydroelectric projects.
          Concerted  efforts  would  be  made  towards  availing  he  funds
          quickly.   This would not only help in preparatin of the bankable
          DPRs for large hydroelectric projects but  would  also  being  in
          advanced    technology   by   involving   reputed   international
          consultants.   The Central organisations  like  CWC,  Brahamputra
          Board,  NEEPCO  and  NHPC,  besides  SEBs  would be provided with
          funding support from the proposed Power Development Fund for  the
          purpose of carrying out survey and investigations and preparation
          of bankable DPRs.

               Since  the  private  sector  has  so  far  been hesitant and
          cautious to invest in hydro projects,  it is  proposed  that  new
          projects   will   initially   be   taken  up  by  CPSUs/SEBs  for
          investigations,  updatation  of  DPRs,  obtaining  the  necessary
          clearances and pre-construction activities.   After these stages,
          the projects could be offered to the private sector for execution
          either on 'stand alone' basis or for joint venture  participation
          with  the  CPSU/SEB.    The expenditure incurred by CPSUs/SEBs on
          these activities would be adjusted in  the  project  cost  to  be
          recovered  from  the  executing  agency  to be decided at a later
          stage.  The Government expects that more private investment would
          be possible with this approach.  In case for a particular project
          no such private investment is forthcoming,  it will  be  executed
          entirely   by   the   concerned   CPSU/SEB  which  initiated  its
          development.

          3.6  Inter-State Projects

               A substantial hydel power potential has remained  locked  up
          and   many  mega  hydel  projects  could  not  be  taken  up  for
          implementation, even though these projects are well recognised as
          attractive and viable,  because of unresolved Inter-State issues.
          Govt.  of  India  recognises the need for evolving an approach to
          ensure that  the  available  hydro-electric  potential  is  fully
          utilised  without  prejudice to the rights of the riparian States
          as determined,  by the Awards of the Tribunals/Agreements arrived
          at  among the party States for a given river basin with regard to
          water sharing.   The selection and design  of  project  would  be
          based  on  integrated  basin wise studies,  so as to arrive at an
          optimal decision and care will be taken that such projects do not
          in any way  prejudice  the  claims  of  basin  states  or  affect
          benefits  from  the  existing  projects.    A  consensus would be
          evolved amongst the basis states regarding the location  of  such
          project.  basic  parameters  involved and mechanism through which
          each project would be  constructed  and  operated.    As  far  as
          possible, there would be preference to take up simple run-of-the-
          river   schemes   that  do  not  involve  any  major  storage  or
          consumptive uses.

          3.7  Renovation, Moderanisation & Uprating

               Renovation,  Moderanisation & Uprating of  old  hydro  power
          plants  is  being accorded priority as it is a faster and cheaper
          way of capacity addition than installing new capacity.    As  per
          recommendations of National Committee set up in 1987 and based on
          the  subsequent  reviews,  55  hydro  schemes  with  an aggregate
          capacity of 9653 MW were identified for RM&U.   Out of these,  20
          hydro  schemes have ben completed providing a benefit of 971.5 MW
          and work on 27 schemes is in progress.   In order  to  provide  a
          greater  thrust  for  RM&U,  Government  would  set up a Standing
          Committee,   to  identify  the  new  schemes  and  for  tying  up
          technology, funding and executing agencies.

          3.8  Promoting Small and Mini Hydel Projects

               The  Ministry of Non-Conventional Energy Sources(MNES) deals
          with all matters related to Small Hydel  Projects  (up  to  3  MW
          capacity).   These projects are being provided with the following
          incentives.

               (i)       Incentives for detailed survey & investigation and
                         preparation of DPR.

               (ii)      Incentives during the  execution of the project in
                         the form of capital/interest subsidy.

               (iii)     Special incentives for  execution of   small hydro
                         projects in  the  North   Eastern   Region  by the
                         Government departmentss/SEBs/State agencies.

               (iv)      Financial support   for renovation,  modernisation
                         and uprating of old small hydro power stations.

               The Small Hydel Projects are site specific and depending  on
          the hydrology,  typically the plant load factor varies from 40 to
          60%.    The  Small  Hydel  Projects  upto  25  MW  will  also  be
          transferred  to  MNES  in order to provide greater thrust for its
          development.   Government of India proposes to provide soft loans
          to  these  projects (up to 25 MW) through IREDA/PFC/REC and other
          financial institutions and Ministry  of  Non-conventional  Energy
          Sources would announce a suitable package of financial incentives
          for  the  accelerated development of Small Hydel Projects upto 25
          MW station capacity.   The State Government and Central and State
          Hydro  Corporations like NHPC/NEEPCO etc.  would be encouraged to
          take up a cluster of small/mini hydel schemes on  Build,  Operate
          and Transfer basis and other suitable arrangements.

          3.9  Simplified Procedures for Transfer of Clearances

               As stated in the foregoing, the CPSUs and the private sector
          would  need  to  play  a greater role in hydro development.   The
          immediate requirement would be to transfer the clearances already
          accorded to non-starting hydro projects in the  State  Sector  in
          favour  of  CPSU/IPP/Joint  Venture of IPP and CPSU.   Government
          would evolve a simple procedure so that  the  transfer  of  CEA's
          techno  economic  clearance would be facile as only updatation of
          project estimate wuld be  examined  by  CEA.    In  the  case  of
          Environment  and  Forest clearances these could be transferred to
          CPSU/IPP etc.  within a prescribed time limit  on  acceptance  of
          conditionalities  stipulated  in the MOEF clearances accorded for
          execution in the State Sector by the  above  executing  agencies.
          Another  inhibiting  factor  discouraging  IPPs  is  the need for
          notification of the scheme as per Section 29 of  ES  Act  in  the
          newspaper  and  Gazette  afresh even if this was done earlier for
          execution by SEBS.   Government intends  to  do  away  with  this
          requirement.    The  simplified procedure as proposed would be an
          encouraging factor for IPP to evince greater  interest  in  hydro
          development.  Government would initiate action right away towards
          this end.

          3.10 Rationalisation of Hydro Tariff

               The  tariff  formulation and norms for hydro projects as per
          existing Government notification are viewed by CPSUs and IPPs  as
          unfavourable  compared to those for thermal projects and the IPPs
          tend to prefer thermal projects for investment.  There is a  need
          to  reformulate  the  principles  on the basis of which tariff is
          determined for hydel generation.   The objective is to fix a rate
          which  will  be  reasonable  to the consumer,  to ensure adequate
          internal resources to repay  the  loan  and  also  to  provide  a
          reasonable  rate  of  return  on  investment.    Recognising  the
          difficulties in execution of hydro projects,  the Government  has
          decided  to rationalise the existing hydro tariff norms,  improve
          the incentives for better operation and evolve a solution to  the
          contentious issue of computing the completion cost in the face of
          geological  uncertainties  and surprises and natural incidents of
          rock slide etc.

               In  January  1995,  the  Government  issued  a  notification
          providing  for  a  two part tariff for hydel generation stations.
          The first part of the tariff,  denominated  as  capacity  charges
          covers  (a)  interest  on  loan  capital;  and  (b)  depreciation
          reckoned at an annual amount  not  exceeding  1/12  of  the  loan
          amount  and  limited  to the actual loan liability of the year as
          per approved financial package.   The second part of  the  tariff
          denominated  as  energy  charges  covers  (a)  return  on  equity
          calculated at 16%  (b) O&M charges ;  (c) tax on income;  and (d)
          any other variable charge.

               Hydro  projects provide valuable peak power andhave inherent
          capability  for  instaneous  starting  and  stoppage   based   on
          variation of load.   The peaking power stations generally operate
          at a very low load level.  Recognising the value of peak power to
          the system and resultant  improvement  in  operation  of  thermal
          stations.  It is proposed to allow a premium on the sale rate for
          hydro  generation  during  peak period.   The formulation of peak
          tariff and the premium to be allowed  would  be  decided  by  the
          Central   Electricity   Regulatory   Commission   and  the  State
          Electricity  Regulatory   Commissions.      Under   the   present
          notification,  the rate for incentive for secondary energy has to
          be fixed at a rate mutually agreed between the State  Electricity
          Board and the generating company.   However,  the maximum payment
          on  this  account  is  restricted  to an amount not exceeding 10%
          return on equity.   In order to provide an  additional  incentive
          for  attracting  investment in hydel projects,  it is proposed to
          allow the sale rate for secondary energy at the same  rate  which
          is applicable for a primary energy.

               Recognising   the  problems  in  operation  of  hydro  power
          stations in the initial years especially  in  project  with  silt
          laden water,  the normative availability factor is proposed to be
          reduced from 90% to 85%.


          3.11 Estimates on Completion Cost (Geological Risks)

               During the implementation of hydro power projects  specially
          underground  power  stations,  there  is  a  likelihood of coming
          across geological surprises which are not anticipated at the time
          of preparation of Detailed  Project  Report.    This  results  in
          increase  in  capital  cost.    The  developer  would  need to be
          compensated for this kind of eventualities.

               In the existing  tariff  notification  for  hydro  projects,
          there is no provision for increase in project cost arising due to
          geological risks.  A realistic estimate of completion cost has to
          take  into  account  the geological and hydrological risks,  cost
          escalation and natural occurrences of  land  slides,  rock  falls
          etc.   In such cases, the developer will be allowed to submit his
          proposal for  the  enhanced  cost  to  the  Government.    Expert
          Committee would be constituted at the State and Central level who
          would evaluate the recommend the cost increases for acceptance by
          the  Government.    The  expert committee at the State Government
          level would recommend the cost  increase  proposal  upto  certain
          percentage and beyond that the cost increase would be recommended
          by the expert committee at the Central Government level.


          3.12 Promoting Hydel Projects with Joint Ventures


               With a view to bring in additional private investment in the
          hydel sector there would be a greater emphasis to take up schemes
          through the joint ventures between the PSUs/SEBs and the domestic
          and foreign private enterprises.   The joint venture company will
          be an  independent  legal  entity  to  be  registered  under  the
          Companies  Act  and  would act as an independent developer.   The
          joint venture agreement  between  the  two  partners  will  bring
          clearly  the  extent of participation by each partner and sharing
          of risks relating to implementation and operation of the project.
          It will also provide for arrangement  in  such  cases  where  the
          joint  venture partner would not be associated with the operation
          and maintenance of the project.   While the selection of a  joint
          venture  partner  would  be  in accordance with the policy of the
          Government, there would be an option for the PSU to either select
          the joint venture  partner  together  with  their  financial  and
          equipment  package  or  to select a joint venture partner wherein
          the EPC contract is decided by both the partners after they  have
          formed  the  joint venture company.   The associated transmission
          line connected  with  the  scheme  will  be  constructed  by  the
          Powergrid  Corporation  of  India.   The power from joint venture
          hydel projects will be purchased by the Power Trading Corporation
          (PTC) proposed  to  be  formed  with  equity  participation  from
          Government/CPSUs/Financial   Institutions.     The  security  for
          payment of power purchased from the joint venture projects  would
          be  through  a LC  to be provided by the SEBS and recourse to the
          State's share of Central Plan Allocation  and  other  devolution.
          This  security  package  would enable to raise finances for these
          projects.   As far as the new schemes to be developed  under  the
          joint  venture route are concerned,  the power sharing formula as
          applicable to the Centre Sector  Projects  shall  not  apply  and
          joint  venture  company would be totally guided by the commercial
          interest.   The State  Government  (home  State/States)  will  be
          compensated  by  way  of 12% free power as per the present policy
          applicable for Central Sector hydel projects.

          3.13 Selection of Developer and Techno Economic Clearance of CEA

               As per Government notification of September,  1996,  all the
          schemes  estimated  to involve a capital expenditure above Rs.100
          crores are to be submitted to CEA for techno  economic  clearance
          and  in  respect  of schemes prepared by a generating company and
          selected  through  a  process  of  competitive  bidding  by   the
          competent  Government  or  Governments,  the exemption from CEA's
          techno-economic clearance is applicable if the  capital  cost  is
          Rs.1000 crores or less.

               Considering  the  capital intensive nature of hydel projects
          especially those of medium  size  being  executed  in  the  State
          Sector, it is proposed to increase the limit for exemption of CEA
          clearance  from the present Rs.100 crores to Rs.250 crores if the
          projects are taken in the MOU route.  In case of projects through
          competitive bidding the existing limit of Rs.1000 crores for  CEA
          techno economic clearance will continue.   However,  irrespective
          of the capital cost or capacity, all hydel projects having inter-
          State aspect will require a mandatory  clearance  from  the  CEA.
          Keeping  in view the need for transparency and cost assessment by
          an accepted mechanism as  well  as  the  uncertainties  that  are
          inevitable  in  the  development and execution of hydel projects,
          the Government proposes  to  allow  the  selection  of  developer
          through  MOU  route for the hydel projects upto 100 MW instead of
          the existing limit of Rs.100 crores.    However,  these  projects
          would require CEA techno economic clearance if their cost exceeds
          Rs.250  crores.    This  would  enable  more developers to evince
          interest in medium size hydro projects due to ease  of  execution
          and   resource   raising   and  due  to  exemption  in  obtaining
          clearances.

          3.14  Govt.  Support  for  Land  Acquisition,   Resettlement and
                Rehabilitation, Catchment Area Development

               The acquisition of requisite Government,  forest and private
          land  involves  cumbersome  procedure  and difficult negotiations
          with land owners to part with the land.   Demands for  employment
          in lieu of the land cost,  land for land at places of land owners
          choice etc.  has resulted in  contractual  problems  for  several
          projects.   There is,  therefore, a need that project authorities
          are insulated from the problems arising out of  land  acquisition
          and  R&R.    It will be the responsibility of the State Govt.  to
          acquire the land (Government/Private/Forest) for the project  and
          also  negotiate  at  its  own  terms  with land owners as per the
          policy adopted by respective State Governments.   Similarly,  all
          the  issues  of  resettlement  and rehabilitation associated with
          projects have to be addressed by  the  State  Govt.    The  State
          Governments  may  consider  to  form  Authorities  to address the
          problems of land  acquisition  and  R&R  for  all  infrastructure
          projects.    In  case  of  mega  projects  the  project  specific
          Authorities may be created not only for land acquisition  and  RR
          but for comprehensive development of the area including catchment
          area.  The project developer may not be involved in execution and
          implementation  of  works  by  these  Authorities,  but  will  be
          required to contribute for funding their plans.   All such  costs
          incurred  by  the  developer  shall  be considered as cost to the
          project and allowed to be passed through tariff.